Quick answer: High-risk construction work (HRCW) is construction work that involves one of 18 activities listed in section 291 of the Work Health and Safety Regulation 2011 (Qld), such as work with a risk of a person falling more than 2 metres, work in or near a trench deeper than 1.5 metres, or work in an area where powered mobile plant is moving. The categories apply only where the activity is construction work. Before high-risk construction work starts, the business carrying it out must ensure a safe work method statement (SWMS) is prepared, and the work must be carried out in line with it.
Not every construction task needs a SWMS, but many more do than people expect. If any part of a job falls into one of the high-risk categories, the SWMS rules apply to that work. This article lists the activities, explains what you have to do, and clears up some common misunderstandings.
The high-risk construction work activities
The list below summarises the 18 categories in section 291. The descriptions are paraphrased, not quoted, so check the regulation for the exact wording. Construction work is high-risk construction work if it:
- involves a risk of a person falling more than 2 metres (other fall duties can still apply below that height)
- is carried out on a telecommunication tower
- involves demolition of an element of a structure that is load-bearing or related to the physical integrity of the structure
- involves, or is likely to involve, disturbing asbestos
- involves structural alteration or repair that requires temporary support to prevent collapse
- is carried out in or near a confined space
- is carried out in or near a shaft or trench deeper than 1.5 metres, or a tunnel
- involves the use of explosives
- is carried out on or near pressurised gas mains or piping
- is carried out on or near chemical, fuel or refrigerant lines
- is carried out on or near energised electrical installations or services
- is carried out in an area that may have a contaminated or flammable atmosphere
- involves tilt-up or precast concrete
- is carried out on, in or next to a road, railway, shipping lane or other traffic corridor in use by traffic other than pedestrians
- is carried out in an area of a workplace where there is any movement of powered mobile plant
- is carried out in areas with artificial extremes of temperature
- is carried out in or near water or other liquid that involves a risk of drowning
- involves diving work
What you must do before the work starts
The business (PCBU) carrying out the high-risk construction work must ensure a SWMS is prepared before the work starts. The SWMS must:
- identify the work that is high-risk construction work
- set out the hazards and risks to health and safety
- describe the control measures, and how they will be put in place, monitored and reviewed
The SWMS should be prepared in consultation with the workers who will do the work, and tailored to the actual work methods and site conditions rather than a generic description of the task.
Doing the work in line with the SWMS
The work must be carried out in accordance with the SWMS. If it isn't, the work must stop as soon as it is safe to do so, and it may only resume once it can be carried out in accordance with the SWMS.
Reviewing the SWMS
The SWMS must be reviewed and, as necessary, revised when the work methods, hazards, control measures or site conditions change, or when a control isn't working.
Keeping the SWMS
The SWMS must be kept, and available for inspection, until the high-risk construction work it applies to is completed. If a notifiable incident occurs in connection with that work, it must be kept for at least 2 years after the incident.
Construction projects and principal contractors
On a construction project, the principal contractor must take all reasonable steps to obtain the SWMS from each contractor before their high-risk construction work starts, and to ensure the work is carried out in accordance with it. Our article on engaging contractors and WHS duties in Queensland explains how duties are shared on site.
Common misunderstandings
- "Every task needs a SWMS." No. Only high-risk construction work needs one. Other work still has to be managed through risk management, but not necessarily with a SWMS.
- "A generic SWMS is fine." A generic template must be adapted to the actual work, methods and site conditions. An unadapted template doesn't meet the purpose of a SWMS.
- "One job means one SWMS." One SWMS can cover several high-risk activities if it addresses each of them, or you can prepare separate SWMS.
- "A SWMS is the same as a risk assessment." They are related but different documents. Our article on the difference between a risk assessment and a SWMS explains when you need each.
Examples
These examples are illustrative. A civil crew installing stormwater pipe in a 2-metre-deep trench beside a busy road is doing high-risk construction work on several counts: the trench is deeper than 1.5 metres, the work is next to a traffic corridor, and an excavator is moving nearby. The depth of the trench alone doesn't establish a risk of falling more than 2 metres, so whether the falls category also applies depends on the actual conditions, such as the depth at the trench edge and what a person could fall onto.
A builder replacing the roof sheeting on an older commercial building faces a risk of falling more than 2 metres, and possibly disturbing asbestos if the existing materials contain it. Falling objects are a related risk on many sites; our article on managing falling object risks covers them.
Queensland also has additional fall protection requirements for some construction work, including housing construction work, which can apply alongside the SWMS rules. Check the specific requirements for your type of work.
High-risk construction work is not the same as high risk work licences
The two are easy to confuse. High-risk construction work is about the type of construction activity, and it triggers the SWMS requirements. High risk work licences are about the person: certain activities, such as operating a forklift or crane or erecting scaffolding above a certain height, need a licence. A single job can involve both.
Need SWMS Developed or Reviewed?
Overwatch Safety Solutions develops and reviews Safe Work Method Statements for construction, civil works, maintenance and other high-risk activities. We help businesses identify applicable high-risk construction work, review existing SWMS and develop practical documentation aligned with actual work activities.
Request a SWMS Review or Development Quote. Contact our team to discuss your activities, documents and project requirements. See our SWMS development page to get in touch.
Frequently asked questions
Does every construction job need a SWMS?
No. A SWMS is only required for high-risk construction work. All other construction work must still be managed through risk management, but a SWMS is not specifically required.
Who prepares the SWMS?
The business carrying out the high-risk construction work must ensure it is prepared, in consultation with the workers who will do the work. On a construction project, the principal contractor must take all reasonable steps to obtain the SWMS before the work starts.
Is high-risk construction work the same as high risk work licensing?
No. High-risk construction work is about the activity and triggers the SWMS requirements. High risk work licences are about the person operating certain plant or doing certain work.
Sources: Work Health and Safety Regulation 2011 (Qld), section 291 (high risk construction work) and sections 299 to 303 (SWMS); Safe Work Australia, High risk construction work requiring a SWMS; WorkSafe Queensland, Interactive SWMS tool.